Checked against primary sources 2026-09-05
Which Wisconsin Electrician License Are You On?
Two questions and this page names the credential your situation points at, what DSPS asks for, what it costs, and the mistake people make on that route. Every path is written out below, so you can read the whole set instead of answering anything.
Test yourself: thirty free questions, timed
Where are you starting from?
Which one are you aiming at?
What are you doing next?
Every path on this page
- Registered Electrician
- Electrical Apprentice
- Residential Journeyman Electrician
- Journeyman Electrician
- Industrial Journeyman Electrician
- Residential Master Electrician
- Master Electrician
- Electrical Contractor
- Licensed in another state
- Renewing
- Moving up a grade
- Renewing late or reinstating
- Taking work in a city I do not know
Registered Electrician BE
This is the entry enrollment that lets you start work legally with no hours behind you, under the direct supervision of a licensed master or journeyman electrician.
SPS 305.45
| Hours | None. SPS 305.45 asks for an application, an application fee and a registration fee, and sets no experience or schooling floor.SPS 305.45 |
|---|---|
| Exam | There isn't one. Neither SPS 305.45 nor form 3108 specifies an examination.SPS 305.45, form 3108 Rev. 01/08/2024 |
| Fees | $15 to apply and $20 for the enrollment.Table 305.02 |
| Term | One year, expiring on the date of issuance, at a $20.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Continuing education | At least 24 hours of acceptable continuing education before the expiration date.SPS 305.45 |
| Supervision | Direct supervision of a licensed Master Electrician or a licensed Journeyman Electrician.DSPS Registered Electrician page |
24 hours of continuing education every year, not every four
SPS 305.45 sets the term at one year and asks for at least 24 hours of acceptable continuing education before the expiration date. A journeyman owes the same 24 hours over four years. That's the heaviest load in the whole Wisconsin set sitting on the credential with the fewest requirements to get, and people who assume it works like the licensed grades find out at renewal. Individuals in a youth apprenticeship program under Wis. Stat. 106.13 are exempt.
SPS 305.45
Electrical Apprentice EA
The apprentice registration is a DSPS credential that sits on top of an apprentice contract you have to get somewhere else first.
SPS 305.46
| Contract | You have to be entered into an electrical apprentice contract recognized under ch. 106, Stats., and renewal asks for that evidence again.SPS 305.46 |
|---|---|
| Exam | There isn't one anywhere in the sequence.SPS 305.46 |
| Fees | $15 to apply and $15 for the registration.Table 305.02 |
| Term | One year, expiring on the date of issuance, at a $15.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Supervision | General supervision of a licensed Master Electrician or a Registered Master Electrician.DSPS Electrical Apprentice page |
| Length | Three official answers. SPS 305.44(3) accepts at least 3 years, DWD publishes about 4 years, and the union committees run 5 years with 8,000 hours on the job.SPS 305.44(3), DWD Construction Electrician page, sponsor committees |
| Continuing education | None is specified in SPS 305.46. Renewal asks instead for evidence that you're still under contract.SPS 305.46 |
Sponsor first, contract second, DSPS registration third
People apply to DSPS and then find they can't finish. The registration is a DSPS credential, but the contract behind it is a Department of Workforce Development matter, registered by the Wisconsin Bureau of Apprenticeship Standards. Form 3102 asks you to upload the contract or proof of electrical indentureship, so you need a sponsor before any of it starts. If you want to be working now rather than waiting on an intake window, the registered electrician enrollment needs no contract at all.
SPS 305.46, form 3102
Residential Journeyman Electrician RJE
This is the shortest route to a licensed card in Wisconsin, three years rather than four, with a scope written around dwellings.
SPS 305.447
| Hours | At least 1,000 hours per year for at least 3 years in residential electrical wiring work, or completion of a recognized residential electrical wiring apprenticeship.SPS 305.447, form 3111 Rev. 01/08/2024 |
|---|---|
| School | A full-time semester counts as 500 hours, capped at 2,000 hours and two years.form 3111 Rev. 01/08/2024 |
| Scope | Wiring associated with dwellings, dwelling units and detached accessory buildings serving them, such as garages, carports, gazebos and swimming pools.form 3111 Rev. 01/08/2024 |
| Exam | Open book, passing score 70 percent, four hours of seat time. DSPS publishes no question count.DSPS exam pages, Pearson VUE trade exam fee schedule |
| Fees | $35 to apply, $30 state examination fee, $100 license fee. Pearson VUE separately prints $95.00 for the exam.Table 305.02, Pearson VUE trade exam fee schedule |
| Term | Four years, expiring June 30, at a $100.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Continuing education | At least 18 hours before the expiration date of the license, against 24 on the general journeyman grade.SPS 305.447 |
The residential card doesn't convert into the general one
There's no exchange route on form 3111. If you later want the general journeyman license, you qualify on SPS 305.44 and sit that examination, which is a wider paper. Form 3111 carries no reciprocity category either, so a residential license from another state buys you nothing here. Only 256 people held this card as an active in state license on 06/01/2026, against 6,791 general journeymen, so think about which one your work actually needs.
form 3111, SPS 305.44
Journeyman Electrician JE
This is the general electrician license, and its scope isn't limited by occupancy or by employer the way the residential and industrial grades are.
SPS 305.44
| Hours | Three routes: a construction electrician apprenticeship of at least 3 years, 8,000 hours over not less than 48 months, or at least 1,000 hours per year for five years.SPS 305.44(3), form 3106 Rev. 12/04/2025 |
|---|---|
| School | A full-time semester counts as 500 hours, capped at 2,000 hours and two years.form 3106 Rev. 12/04/2025 |
| Exam | Open book, passing score 70 percent, four hours of seat time. DSPS publishes no question count.DSPS Journeyman Electrician exam page, Pearson VUE trade exam fee schedule |
| Fees | $35 to apply, $30 state examination fee, $100 license fee. Pearson VUE prints $95.00 for the exam and the two figures don't reconcile.Table 305.02, Pearson VUE trade exam fee schedule |
| Term | Four years, expiring June 30, at a $100.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Continuing education | At least 24 hours of acceptable continuing education before expiration.SPS 305.44(6)(b)1. |
| Supervision | General supervision of a licensed Master Electrician, who stays responsible for the work at all times.DSPS Journeyman Electrician page, Wis. Stat. 101.862(3) |
Come in by apprenticeship and missing your hours costs you the exam
The rule says a person who got the license without passing the journeyman examination, and whose renewal is then denied for failing to meet the continuing education requirement, has to take and pass that examination to get the license back. So the apprenticeship route saves you the exam once and can hand it back years later. The industrial journeyman section carries the same rule. Anyone who sat the exam originally faces an ordinary late renewal instead.
SPS 305.44(6)(b)3.
Industrial Journeyman Electrician IJE
This is the license for an electrician who works inside one company's plant, and its scope stops at the property line of the business that employs you.
SPS 305.443
| Hours | At least 1,000 hours per year for at least 5 years in industrial electrical wiring work, or completion of an industrial electrical apprenticeship.SPS 305.443, form 3105 Rev. 8/14/2024 |
|---|---|
| School | A full-time semester counts as 500 hours, capped at 2,000 hours and two years.SPS 305.443 |
| Scope | Within the facilities or properties of the business establishment where the person is employed, with supervision exceptions for other work.form 3105 Rev. 8/14/2024 |
| Exam | Open book, passing score 70 percent, four hours of seat time.DSPS exam pages, Pearson VUE trade exam fee schedule |
| Fees | $35 to apply, $30 state examination fee, $100 license fee. Pearson VUE separately prints $95.00 for the exam.Table 305.02, Pearson VUE trade exam fee schedule |
| Term | Four years, expiring June 30, at a $100.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Continuing education | At least 18 hours before the expiration date of the license.SPS 305.443 |
A DSPS document request runs out after three months
Form 3105 says documents DSPS asks for "must be uploaded within three (3) months from the date they were requested." Miss that and you resubmit the application and pay the fee again, and SPS 305.02 says the fee isn't refundable. Form 3112 on the residential master side carries the same sentence. There's also no reciprocity category on this form, so an industrial electrician moving into Wisconsin qualifies on hours or an apprenticeship like anybody else.
form 3105 Rev. 8/14/2024
Residential Master Electrician RME
This is a master card with the scope written around dwellings, and it asks two years less than the general master grade.
SPS 305.435
| Hours | At least 1,000 hours per year for at least 5 years in electrical wiring work.SPS 305.435, form 3112 Rev. 01/08/2024 |
|---|---|
| School | A full-time semester counts as 500 hours, capped at 3,000 hours and three years.SPS 305.435 |
| Scope | Wiring associated with dwellings, dwelling units and detached accessory buildings. Non-residential work only under a licensed master or journeyman electrician.form 3112 Rev. 01/08/2024 |
| Exam | Open book, passing score 70 percent, four hours of seat time.DSPS exam pages, Pearson VUE trade exam fee schedule |
| Fees | $35 to apply, $30 state examination fee, $200 license fee. Pearson VUE separately prints $95.00 for the exam.Table 305.02, Pearson VUE trade exam fee schedule |
| Term | Four years, expiring June 30, at a $200.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Continuing education | At least 18 hours of acceptable continuing education, against 24 on the general master grade.SPS 305.435 |
Your hours have to be the kind of work the rule names
The residential master rule counts "electrical wiring work." The general master rule counts "electrical construction work." Those aren't the same phrase, and the difference shows up when a witness signs your experience table for one grade and you later want the other. Worth knowing on the way in: SPS 305.435 lets you exchange this license for a residential journeyman license and back again on application and fee, which is a route no other Wisconsin grade offers.
SPS 305.435, SPS 305.43(2)
Master Electrician ME
The master card carries responsibility for other people's work, and it's the credential a permit gets pulled against.
SPS 305.43
| Hours | SPS 305.43(2) sets at least 1,000 hours per year for 7 years in electrical construction work.SPS 305.43(2) |
|---|---|
| Other routes | Form 3107 Category A also takes 12 months as a licensed Journeyman Electrician, or 10,000 hours over 60 months, or a bachelor's or master's degree in electrical engineering.form 3107 Rev. 12/04/2025 |
| School | A full-time semester counts as 500 hours, capped at 3,000 hours and three years.SPS 305.43(2), form 3107 |
| Exam | Open book, passing score 70 percent, four hours of seat time. DSPS publishes no question count.DSPS Master Electrician exam page, Pearson VUE trade exam fee schedule |
| Fees | $35 to apply, $30 state examination fee, $200 license fee. Pearson VUE separately prints $95.00 for the exam.Table 305.02, Pearson VUE trade exam fee schedule |
| Term | Four years, expiring June 30, at a $200.00 renewal fee.Table 305.06, DSPS renewal schedule |
| Continuing education | At least 24 hours of acceptable continuing education.SPS 305.43(7) |
Two routes on form 3107 get missed
People count toward 10,000 hours when the form doesn't ask them to. A licensed journeyman with twelve months on the card qualifies for the master exam, and a bachelor's or master's degree in electrical engineering qualifies with no hours at all. Read the experience route carefully too, because the 10,000 hours over 60 months and the 1,000 hours a year for seven years are two ways of meeting one route rather than two separate routes.
form 3107 Rev. 12/04/2025
Electrical Contractor EC
This is the license the business holds rather than the person, and it's what lets a company take electrical work in Wisconsin at all.
SPS 305.41
| Exam | There isn't one. No examination is specified in SPS 305.41 or on form 3103.SPS 305.41, form 3103 |
|---|---|
| Who applies | The owner of the business, a partner applying on behalf of the partnership, or the chairman of the board or chief executive officer applying for the corporation.SPS 305.41 |
| Statements | A statement certifying compliance with worker's compensation under ch. 102, Stats., and unemployment compensation under ch. 108, Stats.SPS 305.41 |
| Fees | $35 to apply and $200 for the license, with no examination fee.Table 305.02 |
| Term | Four years, expiring June 30, at a $200.00 renewal fee.DSPS renewal schedule, Rev. 1/4/2024 |
| Continuing education | No requirement is specified in SPS 305.41 for this license.SPS 305.41 |
The contractor license doesn't let anybody do the work
101.862(2) still requires each individual on the job to hold an electrician license or a registered electrician enrollment, and 101.862(3) keeps a master electrician responsible for the work at all times. Milwaukee shows what that looks like on paper, because section 222-13-2-a makes the contractor pulling a permit hand over a copy of its own license and a copy of the master electrician's. Note that the duty covers anyone who offers to engage in the business, so advertising the work is inside it.
Wis. Stat. 101.862
Licensed in another state
Wisconsin's reciprocity rule names no state at all, and the only two that appear anywhere are Iowa and New Hampshire, on two application forms.
SPS 305.47
| The rule | SPS 305.47 is an enabling provision. It says the department "may enter into a reciprocal agreement with another state," and it names nobody.SPS 305.47 |
|---|---|
| Journeyman | Form 3106 Category B takes an Iowa Journeyman A license or a New Hampshire Journeyman Electrician license, held continuously for at least one year immediately before you apply here.form 3106 Rev. 12/04/2025 |
| Master | Form 3107 Category C takes an Iowa Master A license acquired through a state examination in Iowa, held continuously for at least one year.form 3107 Rev. 12/04/2025 |
| No route | Forms 3111, 3105, 3112, 3103 and 3108 carry no reciprocity category, so the residential and industrial grades have none, and neither does contractor or registered electrician.forms 3111, 3105, 3112, 3103, 3108 |
| Fees | $35 to apply either way, then $100 on a journeyman license or $200 on a master license.Table 305.02 |
| Everyone else | Qualify on experience or an apprenticeship, apply in LicensE, and sit the Wisconsin exam.form 3106, SPS 305.44 |
| Temporary license | DSPS publishes an Interstate Reciprocity Temporary License Application. We haven't read it, so we don't describe what it covers or how long it lasts.DSPS Interstate Reciprocity Temporary License Application |
Minnesota and Illinois aren't on the list
Both states border Wisconsin and both send electricians across it, and neither is named on any DSPS form we read. Bordering doesn't create a reciprocal agreement. Read the Iowa credential names closely too, because the journeyman form names the Journeyman A license and the master form names a Master A license acquired through a state examination in Iowa, so an Iowa master license obtained by Iowa's own reciprocity doesn't qualify on the face of the form.
forms 3106 and 3107
Renewing
What you owe at renewal is set by your grade, and the continuing education has to be finished before the expiration date rather than after it.
SPS 305.06
| Term | Four years, expiring June 30, for journeyman, industrial journeyman, residential journeyman, master, residential master and the contractor license.Table 305.06 |
|---|---|
| Short term | One year, expiring on the date of issuance, for the registered electrician enrollment and the apprentice registrations.Table 305.06 |
| Fees | $200.00 for the master grades and the contractor license, $100.00 for the journeyman grades, $20.00 for registered electrician and $15.00 for apprentices.DSPS renewal schedule, Rev. 1/4/2024 |
| Continuing education | 24 hours for journeyman, master and registered electrician. 18 hours for industrial journeyman, residential journeyman and residential master.SPS 305.44(6)(b)1., SPS 305.43(7), SPS 305.45, SPS 305.443, SPS 305.447, SPS 305.435 |
| No expiry | The Registered Master Electrician registration is marked permanent, so it carries no renewal and no renewal hours.Table 305.06, DSPS Registered Master Electrician page |
| Waiver | You can apply for a waiver of the hours on grounds of prolonged illness or disability or similar circumstances, considered individually on its merits.SPS 305.44(6)(b)2. |
A renewal notice you never got isn't an excuse
SPS 305.07 says the department mails a notice at least 30 calendar days before expiration, then says failure to receive one "shall not be considered as an excuse or good cause for failure to renew." Diary the date yourself. The other half people get wrong is timing. The hours have to be done before the expiration date rather than caught up afterwards, and hours used to fix a late renewal can't also be credited toward the next cycle.
SPS 305.07
Moving up a grade
The short route up is twelve months as a licensed Journeyman Electrician, and the scoped licenses don't convert into the general ones.
form 3107 Rev. 12/04/2025
| Journeyman to master | Form 3107 Category A accepts "at least 12 months of experience as a licensed Journeyman Electrician."form 3107 Rev. 12/04/2025 |
|---|---|
| Other master routes | 10,000 hours over 60 months or 1,000 hours a year for seven years, or a bachelor's or master's degree in electrical engineering with no hours at all.form 3107, SPS 305.43(2) |
| Residential pair | SPS 305.435 lets you exchange a residential master license for a residential journeyman license and back again, on application and fee.SPS 305.435 |
| Residential to general | No exchange route exists on form 3111. You qualify on SPS 305.44 and sit that examination.form 3111, SPS 305.44 |
| Exam and fees | Open book at 70 percent, $35 to apply, $30 state examination fee, then $200 on a master license.Table 305.02, DSPS Master Electrician exam page |
| Route back | Form 3107 Category B covers a Wisconsin master license that had been exchanged for a journeyman license, which is a route back rather than a route in.form 3107 Rev. 12/04/2025 |
A scoped license isn't a rung on the general ladder
Residential journeyman and industrial journeyman are separate licenses with their own scopes, not lower grades of the journeyman license. Neither form carries an exchange into the general grade, so you qualify under SPS 305.44 and sit the journeyman paper the same as anybody else. Hours you worked inside one plant or on dwellings still count as hours, but they have to be witnessed on the experience table for the grade you're applying for.
form 3111, form 3105
Renewing late or reinstating
What a late renewal costs depends on whether you're inside one term after expiration or past it.
SPS 305.07
| Within one term | You pay an application fee under Table 305.02 and document continuing education obtained after expiration, with a $25.00 processing fee to file the late continuing education form.SPS 305.07 |
|---|---|
| Past one term | Reinstatement runs on an administrative fee of $200.00, an application and the application fee.SPS 305.07 |
| Competence | The department may require a demonstration of competence through examination or documented work experience.SPS 305.07 |
| Fees | The renewal schedule prints a $200.00 reinstatement fee for electrical credentials and a $25.00 late continuing education fee.DSPS renewal schedule, Rev. 1/4/2024 |
| Refunds | None. SPS 305.02 says fees for licenses, registrations, enrollment and examination processing are not refundable.SPS 305.02 |
| Hours | A course taken to fulfill late renewal obligations can't be credited toward more than one renewal cycle.SPS 305.08 |
Apprenticeship graduates who miss the hours have to sit the exam
If you got the journeyman license without passing the journeyman examination, and renewal is denied for failing to meet the continuing education requirement, the rule requires you to take and pass that examination to get the license back. The industrial journeyman section says the same thing. So a late renewal costs an apprenticeship graduate the card and the exam, while a licensee who sat the exam originally is looking at a fee and a form.
SPS 305.44(6)(b)3.
Taking work in a city I do not know
Every city we checked routes licensing back to the DSPS credential and keeps permits and inspections for itself.
Milwaukee Code of Ordinances Chapter 222
| Milwaukee | Chapter 222 adopts "chs. SPS 305, SPS 316 and SPS 318, Wis. Adm. Code, as amended," and limits the work to a state-licensed electrical contractor or a person exempt under 101.862(4).Milwaukee Code of Ordinances, 222-01 and 222-1-1-b |
|---|---|
| Permits | Section 222-13-2-a makes the contractor pulling a permit supply its own license and a copy of the license of the master electrician taking full responsibility.Milwaukee Code of Ordinances, 222-13-2-a |
| Green Bay | Its FAQ says the work must be done by "an electrical contractor licensed in Green Bay," while its own permit application asks for a State of WI Electrical Contractor Certification number and a WI Master Certification number.Green Bay FAQ and licensed contractor electrical permit application |
| Madison | The city's list of licenses and permits carries no electrical entry, though it lists plumbers and water contractors. Its Chapter 19 Electrical Code wouldn't load for us, so its wording is unconfirmed.City of Madison licenses and permits list |
| Kenosha and Appleton | Kenosha asks contractors doing electrical work for a Wisconsin Master Electrician license and a Wisconsin Electrical Contractor license. Appleton's permit form asks for a State Electrical Contractors number and a State/Masters License number. Neither describes a city license.Kenosha licensing requirements form, Appleton electrical permit form |
| Stale city copy | Milwaukee's Electrical Inspection Section page says "Currently, the state has adopted the 2011 National Electrical code," which is two cycles out of date. The ordinance adopts the state chapters as amended, so the ordinance is right and the page is old.Milwaukee Electrical Inspection Section page, Chapter 222 |
City wording can sound like a city license when it isn't one
Green Bay tells you the work must be done by an electrical contractor licensed in Green Bay, and its own permit application then asks for a State of WI Electrical Contractor Certification number and a WI Master Certification number. Those are state credentials. Ask the inspection office two questions before you work somewhere new: who may pull an electrical permit here, and what do you want to see on the application. If a city tells you something different, get it in writing.
Green Bay FAQ and permit application
This is a reading of DSPS material, and it is not advice and not an application. Check anything that decides money or a deadline against the source named beside it.
The 2023 to 2026 section crosswalk maps every section that moved, both directions, $29 once.